Epic Goal
Establish solid technical foundation before building features. This epic tracks all foundational work required for subsequent sprints.
Success Criteria
Sprint Capacity
- Total Available: 60 hours (2 devs × 5 days × 6 hrs)
- Planned: 42 hours (70% capacity)
- Buffer: 18 hours for incidents/unknowns
Stories
- Database Schema & Migrations (5 pts)
- Svelte 5 Environment Setup (8 pts)
- pnpm Workspaces & Monorepo (5 pts)
- Auth Service API (5 pts)
- Developer Experience & CI/CD (3 pts)
Total: 26 points
Risks
| Risk |
Probability |
Mitigation |
| Svelte 5 migration complexity |
Medium |
Time-box spike, reduce scope if needed |
| Database migration conflicts |
Low |
Use migrations from day 1 |
| Auth complexity |
Medium |
Cut scope (rate limiting optional) |
Definition of Done (Epic)
Epic Goal
Establish solid technical foundation before building features. This epic tracks all foundational work required for subsequent sprints.
Success Criteria
Sprint Capacity
Stories
Total: 26 points
Risks
Definition of Done (Epic)